California's Net Billing Tariff (NEM 3.0), explained from the tariffs

Since April 15, 2023, new rooftop solar customers of PG&E, SCE and SDG&E have been on the Net Billing Tariff, the successor to net metering that most people call NEM 3.0.1 Exports are no longer netted against imports; each exported kilowatt-hour earns an hourly value from the CPUC's Avoided Cost Calculator, locked for nine years for customers who apply by the end of 2027.2 Customers already on NEM 1.0 or NEM 2.0 keep their tariff for 20 years from interconnection.5

Published November 16, 2026. Rules checked November 16, 2026.

West region, Pacific division

Who is on the Net Billing Tariff

The California Public Utilities Commission adopted Decision 22-12-056 on December 15, 2022, creating the Net Billing Tariff as the successor to NEM 2.0, and the tariff applies to customers who submit an interconnection application on or after April 15, 2023.1 The utilities call it the Solar Billing Plan in customer communications.2

It covers the three large investor-owned utilities: Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric. Publicly owned utilities such as LADWP and SMUD are outside the decision and run their own programs.34

Customers who connected under the earlier tariffs keep them. PG&E's NEM2 schedule lets customers stay for 20 years from the year their system was first interconnected, measured from the date they received permission to operate.5

Net metering rules in California at a glance
RuleWhat applies
Program typeNet billing Exports are credited at a separate export rate, usually below the retail rate, with little or no netting.
ProgramNet Billing Tariff (Solar Billing Plan)
How exports are creditedExports valued at hourly Avoided Cost Calculator values; early applicants also get a declining ACC Plus adder34
Netting intervalNone (imports and exports metered separately)
Unused creditsCredits roll to an annual true-up; any net surplus is paid at the Net Surplus Compensation rate
InstrumentCPUC Decision 22-12-056
In effectInterconnection applications from April 15, 2023
CheckedNovember 16, 2026

How exports are valued

The core change is that exports and imports no longer cancel each other. PG&E's tariff says imports and exports are recorded on separate import and export channels "and are not netted".2 Every kilowatt-hour you take from the grid is billed at your time-of-use rate; every kilowatt-hour you send earns an export credit.

That credit comes from the CPUC's Avoided Cost Calculator, a model of what the utility saves when a kilowatt-hour arrives from a rooftop instead of from its usual supply. Values differ by hour, by month and between weekdays and weekends.43 For customers who apply between April 15, 2023 and December 31, 2027, the tariff locks in a nine-year schedule of hourly values from the calculator adopted as of January 1 of the application year.2

The spread inside a year is wide. In PG&E's 2026 price sheet the generation value of an exported kWh ranges from $0.00000 to $1.04281 depending on the hour, with the highest values in late-summer evenings.6 Solar panels produce most at midday in spring, when values are lowest. That is why the tariff rewards a battery that stores midday output and exports it, or uses it, in the evening.

The ACC Plus adder for early applicants

To soften the change, the decision added a fixed "ACC Plus" adder on top of the hourly values for customers who join in the first five years. The initial residential adders were $0.022 per kWh at PG&E, $0.040 at SCE and $0.000 at SDG&E, higher for CARE (low-income) customers at PG&E and SCE.7 SDG&E's residential customers get no adder at all.8

The adder shrinks for each new application year and stays fixed for nine years once you have it. At PG&E it is $0.0088 per kWh for 2026 applications and $0.0044 for 2027, then ends; for low-income customers it is $0.0360 in 2026 and $0.0180 in 2027.2 SCE's 2026 vintage adder is $0.016 per kWh, falling to zero for 2028 and later.9

PG&E in California: solar export rules
RuleWhat applies
Program typeNet billing
ProgramNet Billing Tariff (Schedule NBT, "Solar Billing Plan")
Export creditHourly Avoided Cost Calculator export values; ACC Plus adder of $0.0088/kWh for 2026 applications2
Netting intervalNone
Unused credits and chargesAnnual true-up; leftover credit rolls forward by default, check on request if over $1

Bills, true-up and leftover credits

You pay charges net of credits every month, and all charges and credits are trued up once a year. Export credits can offset the volumetric (per-kWh) charges on your imports, but not the non-bypassable charges that every customer pays on each kWh taken from the grid.2

What happens to a credit balance at true-up differs by utility. At PG&E, any remaining Net Surplus Compensation rolls forward by default, and you can ask for a check if it is more than $1.2 At SCE, export credits left after the annual settlement are forfeited; only customers with surplus kWh for the year receive Net Surplus Compensation.9

The rate you must take

Net billing customers do not choose freely among rate plans. PG&E requires residential NBT customers to take its E-ELEC time-of-use rate,2 and SCE requires the Prime option of its TOU-D rate.9

Those rates carry an income-graduated Base Services Charge that every residential customer pays, solar or not. On PG&E's E-ELEC it is $0.79343 a day for most customers (Income Tier 3), $0.39688 for Tier 2 and $0.19713 for CARE customers.10 The CPUC's implementation schedule set the monthly tiers at $24.15, $12.08 and $6.00, introduced in the fourth quarter of 2025 at SCE and SDG&E and the first quarter of 2026 at PG&E.311 Export credits do not pay it.

How big a system the tariff allows

A net billing system must be intended primarily to offset your own use, but the tariff lets you size up for electrification you expect, such as an electric car or heat pump, if you sign an oversized generating facility attestation.2 The CPUC sets the limit at your annual load plus up to 50% when you attest to the need.3

Batteries under net billing

Storage paired with a net billing system is allowed, and PG&E gives paired storage the same interconnection cost treatment as the solar generator it is paired with.2 SCE exempts paired storage from supplemental review fees, detailed study costs and distribution upgrade costs under its tariff.9

California has the most paired batteries in the country: utilities reported 328,49212 residential batteries paired with net-metered solar at the end of 2025. The state's Self-Generation Incentive Program offers equity incentives for low-income households, open for reservation from June 2, 2025.13

Batteries paired with net-metered solar, homes, 2025: top 10

Source: Energy Information Administration, Form EIA-861 Annual Electric Power Industry Report, 2025 final data. Residential PV-paired battery installations reported by utilities. Bar colour: program type.

Show the numbers
StateBatteries paired with net-metered solar, homes, 2025
California328K
Hawaii20K
Arizona18K
Utah12K
Texas5,395
Florida5,292
Michigan4,884
New York4,786
Washington3,888
Nevada3,639
New Jersey2,803
Massachusetts2,674
Oregon2,459
Ohio1,943
Colorado1,712
Pennsylvania1,482
Rhode Island1,406
South Carolina1,100
Virginia901
Missouri827
Wisconsin800
New Hampshire777
Maryland753
West Virginia724
Indiana718
Idaho704
Kentucky564
Georgia491
Oklahoma437
North Carolina430
Montana395
Wyoming190
New Mexico133
Minnesota129
Maine114
Arkansas46
Connecticut46
Delaware41
Tennessee39
Illinois30
Iowa23
Nebraska14
Mississippi11
Louisiana4
Kansas2
Alabama0
Alaska0
District of Columbia0
North Dakota0
South Dakota0
Vermont0

What changes next

Two dates in the tariff matter. Applications submitted after December 31, 2027 no longer lock in nine years of export values, and the ACC Plus adder reaches zero for new customers after the 2027 application year.2 The CPUC updates the Avoided Cost Calculator periodically, so later applicants take newer values.

Separately, California's property tax exclusion for newly built active solar energy systems is scheduled to sunset on January 1, 2027.14

What changed and when
DateWhereWhat changed
December 15, 2022CaliforniaCPUC adopts the Net Billing Tariff. Decision 22-12-056 replaced NEM 2.0 for new customers of PG&E, SCE and SDG&E with net billing at Avoided Cost Calculator values.134
April 15, 2023CaliforniaNet billing applies to new California solar applications. Customers of the three large investor-owned utilities applying for interconnection on or after April 15, 2023 take service on the Net Billing Tariff.134
June 1, 2026CaliforniaSMUD raises its export rate. SMUD’s Export Compensation Rate became $0.0960/kWh under Rate Schedule SSR.15
December 31, 2027CaliforniaLast day to apply for California net billing with a nine-year lock. PG&E’s tariff locks nine years of export values for applications submitted through December 31, 2027.2

California solar by the numbers

California has 2,309,938 net-metering customers, the highest total of any state, and PG&E alone has 931,269 net-metered homes, 41%12 of the state's residential installations. EIA's 2025 count still includes many customers on the earlier tariffs; utilities may report net billing customers outside the net metering table.

Residential net-metering installations by utility, California, 2025
Imperial Irrigation District14,066
City of Roseville - (CA)13,542
Modesto Irrigation District11,986

Source: Energy Information Administration, Form EIA-861 Annual Electric Power Industry Report, 2025 final data. EIA-861 utility rows, all technologies; utility names as reported to EIA.

Show the numbers
UtilityResidential installations
Pacific Gas & Electric Co.931,269
Southern California Edison Co734,901
San Diego Gas & Electric Co341,292
Los Angeles Department of Water & Power95,898
Sacramento Municipal Util Dist63,218
Imperial Irrigation District14,066
City of Roseville - (CA)13,542
Modesto Irrigation District11,986
City of Riverside - (CA)7,975
Turlock Irrigation District5,418
City of Anaheim - (CA)5,351
City of Glendale - (CA)3,874
City of Moreno Valley - (CA)3,653
Merced Irrigation District3,623
City of Pasadena - (CA)3,121
City of Redding - (CA)2,332
City of Burbank Water and Power - (CA)1,899
City of Palo Alto - (CA)1,763
Alameda Municipal Power1,235
City of Santa Clara - (CA)1,233
City of Colton - (CA)1,211
PacifiCorp998
Liberty Utilities931
Bear Valley Electric Service684
City of Lodi - (CA)643
City of Azusa464
City of Shasta Lake - (CA)146
City & County of San Francisco - (CA)21
City of Corona - (CA)20
Surprise Valley Electrification18
Net-metering customers in California, 2010–2025
Net-metering customers in California, 2010–202501M2M201020132016201920222025

Source: Energy Information Administration, Form EIA-861 Annual Electric Power Industry Report, net metering 2010–2025. Customers on a net-metering tariff, all sectors and technologies, end of each year. EIA counted meters in 2010–2012, customers in 2013–2024 and installations in 2025; customers on net billing may be reported outside this count.

Show the numbers
YearCustomers
201086,495
2011115,921
2012159,708
2013234,025
2014338,044
2015501,254
2016671,503
2017816,896
2018946,820
20191,104,744
20201,260,349
20211,448,203
20221,699,177
20231,982,299
20242,152,476
20252,309,938

Utility pages: PG&E, SCE, SDG&E, LADWP and SMUD. The state overview is on the California net metering page.

Questions and answers

Is NEM 3.0 retroactive?

No. The Net Billing Tariff applies to customers who submit an interconnection application on or after April 15, 2023.1 Customers on NEM 1.0 or NEM 2.0 stay on their tariff for 20 years from the date they first received permission to operate.5

What is the difference between NEM 2.0 and NEM 3.0?

Under NEM 2.0, exports offset imports kilowatt-hour for kilowatt-hour at the retail rate, with non-bypassable charges paid on every kWh imported.5 Under the Net Billing Tariff, imports and exports are recorded separately and not netted; exports earn hourly avoided-cost values instead of the retail rate.2

Does NEM 3.0 apply to SMUD or LADWP customers?

No. Decision 22-12-056 covers PG&E, SCE and SDG&E. Publicly owned utilities set their own programs; LADWP still runs net energy metering under its own rate ordinance,17 and SMUD credits exports at a flat export compensation rate.15

What happens to the nine-year lock if I sell my house?

The CPUC tied the legacy period to the customer who originally causes the system to be installed, not to the system itself, so the lock does not pass to the buyer with the house.3418

How do I find the export values for my hours?

Each utility publishes its export value tables by application year. PG&E's 2026 sheet lists values for every hour of each month, with separate weekday and weekend tables.6

Related pages

Sources

  1. CPUC – Net Billing Tariff page, CPUC web page. On December 15, 2022, the CPUC adopted D.22-12-056, establishing the Net Billing tariff (NBT) as a successor to NEM2. ... The NBT will apply to customers who submit an interconnection application on or after April 15, 2023. Checked November 16, 2026. cpuc.ca.gov
  2. PG&E Electric Schedule NBT – Net Billing Tariff (NBT) Service, Cal. P.U.C. Sheets 55440-E et seq.; Advice 6848-E (eff. 2023-03-01), Advice 7174-E (eff. 2024-02-15); CPUC D.22-12-056, D.23-11-068. The NBT schedule may also be referred to as the Solar Billing Plan in customer-facing communications. Residential customers, including Load Aggregation Generating/Aggregated Accounts, taking service on NBT must take service on the E-ELEC (ELECTRIC HOME) rate schedule … For both residential and … Checked November 16, 2026. pge.com
  3. CPUC, Net Energy Metering and Net Billing - Key Information. Effective: 2023-04-15. Since April 15, 2023, customers applying for interconnection have taken service on the new net billing tariff (NBT) pursuant to D.22-12-056 . ... The IOUs refer to the NBT as the “Solar Billing Plan.” ... Pursuant to D.14-03-041 , customer-generators are allowed to remain on the NEM 2.0 tariff for … Checked November 16, 2026. cpuc.ca.gov
  4. CPUC Decision 22-12-056 (R.20-08-020), Ordering Paragraph 1. Effective: Decision 2022-12-15; tariff 2023-04-15. A net billing tariff is adopted. Imports and exports will be calculated based on no netting of consumption and production and will be trued-up on an annual basis. ... The ACC Plus will be available to net billing tariff customers during the first five years of the successor tariff, as a glide path. … Checked November 16, 2026. docs.cpuc.ca.gov
  5. PG&E Electric Schedule NEM2 – Net Energy Metering Service, Cal. P.U.C. Sheet 59228-E (Sheet 46) et seq.; CPUC D.16-01-044. are eligible to continue receiving service on this NEM2 Schedule for a period of 20 years from the original year in which their Generating Facility was interconnected to PG&E’s grid, indicated by and measured from the date on which the Customer originally received Permission To Operate (PTO) … … Checked November 16, 2026. pge.com
  6. PG&E Solar Billing Plan – 2026 Energy Export Credit (EEC) Values price sheet, PDF "PGE_Solar Billing Plan_EEC Values Price Sheet 2026.pdf" inside the ZIP. Pricing reflects the average EEC values determined by the California Public Utilities Commission. ... Energy Produced credits are only applicable to Solar Billing Plan customers who receive bundled generation service from PG&E. Checked November 16, 2026. pge.com
  7. CPUC Decision 22-12-056, D.22-12-056 (issued Dec 19, 2022). Table 7. Adopted Initial ACC Plus Adders by Utility ($/kWh) Customer Segment PG&E SDG&E SCE Residential Non-CARE $0.022 $0.000 $0.040 Residential CARE $0.090 $0.000 $0.093 Commercial (not eligible) $0.000 $0.000 $0.000 Checked November 16, 2026. docs.cpuc.ca.gov
  8. CPUC Decision 22-12-056, Decision Revising Net Energy Metering Tariff and Subtariffs (R.20-08-020), issued Dec. 19, 2022, D.22-12-056, Table 7 and §8. Table 7. Adopted Initial ACC Plus Adders by Utility ($/kWh) Customer Segment PG&E SDG&E SCE Residential Non-CARE $0.022 $0.000 $0.040 Residential CARE $0.090 $0.000 $0.093 … Because SDG&E net billing tariff customers will have payback periods of less than nine years, the graph does not indicate a glide path. Checked November 16, 2026. docs.cpuc.ca.gov
  9. SCE Schedule NBT – Net Billing Tariff, Cal. PUC Sheets 85375-E et seq. (e.g., Sheet 30 = 87700-E); Advice 4961-E/4961-E-A (eff. 2023-03-01), 5170-E-A (eff. 2023-12-14), 5228-E (eff. 2024-02-15), 5533-E (eff. 2025-04-23); D.22-12-056; D.23-11-068. Residential Customers taking service under this Schedule must be on the Prime Option of Schedule TOU-D. … multiplying the hourly-differentiated Customer’s Energy Export (channel 2) in kWh by the applicable Energy Export Credit Price (EEC Price), as defined below, derived from the approved Avoided … Checked November 16, 2026. sce.com
  10. PG&E Electric Schedule E-ELEC – Residential Time-of-Use (Electric Home), Rates sheet: Advice 7921-E, D.26-04-036, effective 2026-06-01; Special conditions Advice 7846-E effective 2026-03-01; Sheet 61118-E. Base Services Charge Rates ($ per customer per day) Income Tier 1 $0.19713 (N) Income Tier 2 $0.39688 (N) Income Tier 3 $0.79343 (N) Checked November 16, 2026. pge.com
  11. CPUC Energy Division, Update on the Implementation of the BSC (LIOB, Dec 2025). Effective: Q4 2025 / Q1 2026. Implementation of BSC: Q4 2025 (SCE and SDG&E), Q1 2026 (PG&E) ... 1 $6.00 CARE Status ... 2 $12.08 FERA ... 3 $24.15 Non- CARE/FERA Checked November 16, 2026. liob.cpuc.ca.gov
  12. Energy Information Administration, Form EIA-861 Annual Electric Power Industry Report, 2025 final data, Net_Metering_2025.xlsx (f8612025.zip), released October 7, 2026. eia.gov
  13. CPUC, Self-Generation Incentive Program. Effective: 2025-06-02. The Residential Solar and Storage Equity Incentives Are Available for Reservation Beginning June 2, 2025. Available to any low-income residential electric and/or gas customer in California. Checked November 16, 2026. cpuc.ca.gov
  14. California BOE, Active Solar Energy System Exclusion. Effective: until 2027-01-01. Effective September 18, 2022, the sunset date for the active solar energy system new construction exclusion was extended through 2025-26 fiscal year. The statute is now scheduled to sunset on January 1, 2027. Checked November 16, 2026. boe.ca.gov
  15. SMUD Rate Schedule SSR – Solar and Storage Rate, Sheets SSR-1 to SSR-3; Resolution No. 21-09-07 (Sept 16, 2021) as amended by Resolution No. 26-04-04 (April 16, 2026); effective June 1, 2026. This Rate Schedule SSR applies to residential, commercial/industrial, and agricultural customers who establish service at a premises that has an electrical generation facility that is fueled by a renewable fuel source on or after March 1, 2022 … The Export Compensation Rate effective June 1, 2026 … Checked November 16, 2026. smud.org
  16. Energy Information Administration, Form EIA-861 Annual Electric Power Industry Report, net metering 2010–2025, Net_Metering sheets of the annual files, released October 7, 2026. eia.gov
  17. LADWP Electric Rates (rate ordinance, consolidated PDF hosted by LADWP), Service Rider NEM, "Rate Effective September 1, 2008" (ordinance adopting Resolution No. 009-009 of July 2, 2008); later ordinances may have amended rates — check current ordinance. Customer owns and operates a permanent solar or wind turbine electrical generating facility or a hybrid system with a capacity of not more than one megawatt that is located on the customers premises … A credit for the energy received will be calculated using the applicable Rate Schedule energy … Checked November 16, 2026. ladwp.com
  18. Senate Energy, Utilities & Communications Committee analysis of AB 942 (hearing 7/15/2025). Effective: pending/unknown. This bill modifies the terms applicable to customer-generators participating in the Net Energy Metering (NEM) tariff, including by requiring customer-generators of electrical corporations to be transferred to a new tariff when the property has been sold Checked November 16, 2026. seuc.senate.ca.gov

Rules are quoted from the official text and dated; how we check them: methodology. Not legal or tax advice. Found an error? Write to [email protected]; corrections are listed on the updates page.