Mississippi net metering: an avoided-cost credit with a fixed adder
Published November 16, 2026. Rules checked November 16, 2026.
Net billingMississippi Power Rate Schedule RENM-3 · May 27, 2025 (RENM-3)
Net renewable generation (avoided cost plus adder). Exports credited at the basic avoided energy cost plus a 2.5¢/kWh distributed generation value, fixed for 25 years.2 Unused credits: set by tariff option. EIA counted 2,030 homes on net metering in Mississippi at the end of 2025.1
Rules checked November 16, 2026 against the official text; EIA-861 2025 final data, released October 7, 2026.
South region, East South Central division
Mississippi Power's rooftop solar schedule carries the words "net metering" in its title, but exported power is not swapped kilowatt-hour for kilowatt-hour. The company credits each exported kWh at its basic avoided energy cost plus a 2.5¢ per kWh Distributed Generation Value that stays in place for 25 years from installation, with 2.0¢ more for low-to-moderate income households.2
A "net metering" schedule that credits exports separately
The schedule behind "Mississippi Power net metering" is the company's Renewable Energy Net Metering Rate Schedule, RENM-3, filed as Mississippi Public Service Commission Schedule No. 59. Despite its title, it does not let an exported kilowatt-hour cancel a kilowatt-hour bought later. It prices exports: the company credits energy delivered to the grid at its basic avoided energy cost, adjusted upward by a fixed adder.2
That makes the schedule net billing, and it is why Mississippi is classed here as a net billing state. Net billing means each exported kWh is credited at a separate export rate instead of offsetting a purchase at the retail price. The panels' output used inside the house at the moment it is produced never shows up as a purchase, so it still avoids the full retail price; only the surplus that flows out through the meter earns the export credit. The yardstick for that comparison is the residential average, 14.85¢ per kWh3 in Mississippi over the 12 months to August 2026 with fixed charges included. That average divides utility revenue by kilowatt-hours sold and is not a tariff rate. For the general difference between the two designs, see net billing vs net metering.
| Rule | What applies |
|---|---|
| Program type | Net billing Exports are credited at a separate export rate, usually below the retail rate, with little or no netting. |
| Program | Net renewable generation (avoided cost plus adder) |
| How exports are credited | Exports credited at the basic avoided energy cost plus a 2.5¢/kWh distributed generation value, fixed for 25 years2 |
| Netting interval | Set by tariff option |
| Unused credits | Set by tariff option |
| Instrument | Mississippi Power Rate Schedule RENM-3 |
| In effect | May 27, 2025 (RENM-3) |
| Checked | November 16, 2026 |
The adder is not a Mississippi Power invention. RENM-3 says the upward adjustment is the "Distributed Generation Value, as defined in the MDGR", the Mississippi Distributed Generation Rule that the schedule names as governing every installation (RENM-3, Mississippi Power).2
The three layers of an export credit
An exported kilowatt-hour on Mississippi Power is valued in up to three pieces. Each one has its own basis and its own clock.2
| Layer | Amount | Who gets it | How long |
|---|---|---|---|
| Basic avoided energy cost | the company's avoided energy cost rate | every participant | not fixed by the schedule |
| Distributed Generation Value | 2.5¢ per kWh2 | all participants | 25 years from the date of installation |
| Low-to-moderate income adder | 2.0¢ per kWh more | households at or below 225% of the Federal Poverty Level | 25 years |
The first layer is the company's basic avoided energy cost: what the utility saves by not producing or buying that energy itself. It is not the retail rate a household pays, and the schedule does not lock it in. The second and third layers are fixed amounts per kWh, and the schedule ties them to the individual system: the 2.5¢ adder "will remain in place for twenty-five (25) years from the date of installation."2
A household that qualifies as low-to-moderate income, with income at or below 225% of the Federal Poverty Level, receives the extra 2.0¢ per kWh on top of the other two layers for 25 years.2
RENM-3 also gives the customer a choice of two billing options, Option A and Option B.2 How each one measures exports and treats a credit larger than the month's charges is written in the schedule itself, which is the document to read before choosing.
Who RENM-3 covers, and who it does not
RENM-3 is one utility's tariff. It sets the terms for Mississippi Power customers; it does not set the bill of a customer of any other utility.2 That matters because Mississippi Power is not the state's largest solar utility by residential installations.
Entergy Mississippi reported 794 residential net-metering installations to EIA at the end of 2025, 39%1 of the state's total, more than any other utility. Its customers searching "Entergy Mississippi net metering" need Entergy Mississippi's own schedule, which sets their terms; RENM-3 does not, and its avoided-cost base and billing options should not be assumed to carry over.
The rest of the state's solar homes are spread across electric power associations and cooperatives. Coast Electric Power Association reported the third-largest count, followed by Pearl River Valley, Magnolia, Southern Pine and Dixie. 81 Mississippi utilities in all reported at least one residential net-metered installation. A member of a power association or cooperative should ask it for its distributed generation schedule and read it before signing a solar contract.
Source: Energy Information Administration, Form EIA-861 Annual Electric Power Industry Report, 2025 final data. EIA-861 utility rows, all technologies; utility names as reported to EIA.
Show the numbers
| Utility | Residential installations |
|---|---|
| Entergy Mississippi LLC | 794 |
| Mississippi Power Co | 530 |
| Coast Electric Power Assn - (MS) | 414 |
| Pearl River Valley El Pwr Assn | 111 |
| Magnolia Electric Power Assn | 79 |
| Southern Pine Electric Cooperative | 57 |
| Dixie Electric Power Assn - (MS) | 41 |
| Delta Electric Power Assn | 4 |
The utility finder shows which utility serves an address.
System size: 110% of peak or 20 kW
Mississippi Power limits a home system on RENM-3 to the lesser of 110% of the customer's annual peak demand or 20 kW, measured as nameplate direct current capacity. Non-residential customers may go up to the lesser of 110% of annual peak demand or 2 MW.2
The 110% test ties the system to the home's own highest demand, so the 20 kW figure is a ceiling, not an entitlement: a house with a modest peak load qualifies for less. A residential system above 20 kW and up to 100 kW is not shut out entirely: it may take service under the company's Cogeneration and Small Power Production (CSPP) schedule instead.2
The May 2025 revision and the 25-year clock
The current schedule took effect on May 27, 2025 and replaced the version dated March 16, 2023. An article, quote or proposal that cites the March 2023 version describes a superseded schedule.2
| Date | Where | What changed |
|---|---|---|
| May 27, 2025 | Mississippi | Mississippi Power’s RENM-3 net metering schedule takes effect. RENM-3 superseded the 2023 version of the schedule.2 |
There is no single statewide sunset date for existing customers. Protection is per system: the 2.5¢ adder runs for 25 years from each installation's own date, so a system connected earlier reaches the end of its adder earlier than one connected later. The 25-year term in the schedule attaches to the adders, not to the avoided-cost base.2
For how other states handle legacy customers, see grandfathering and legacy tariffs.
One of the smallest solar markets, growing quickly
Mississippi has 2,154 net-metering customers, 5th lowest among the 50 states and DC. About 0.1 residential installations exist for every 100 residential electric accounts, an estimate built from two different counts, which also ranks 5th lowest1. EIA's preliminary monthly series counted 1,9104 solar net-metering customers in August 2026; it is a different survey from the annual count and the two are not directly comparable.
The base is small, but it has more than tripled. Utilities reported 660 net-metering customers in 2020 and 1,899 at the end of 2024, an increase of 226%5 over five years to the end of 2025.
Source: Energy Information Administration, Form EIA-861 Annual Electric Power Industry Report, net metering 2010–2025. Customers on a net-metering tariff, all sectors and technologies, end of each year. EIA counted meters in 2010–2012, customers in 2013–2024 and installations in 2025; customers on net billing may be reported outside this count.
Show the numbers
| Year | Customers |
|---|---|
| 2010 | 1 |
| 2011 | 6 |
| 2012 | 5 |
| 2013 | 15 |
| 2014 | 27 |
| 2015 | 26 |
| 2016 | 179 |
| 2017 | 295 |
| 2018 | 437 |
| 2019 | 570 |
| 2020 | 660 |
| 2021 | 818 |
| 2022 | 1,028 |
| 2023 | 1,271 |
| 2024 | 1,899 |
| 2025 | 2,154 |
Homes on Mississippi Power carry more solar capacity in total than Entergy Mississippi's larger number of homes, according to the same EIA utility data. Statewide, residential systems total 11 MW out of 17 MW1 of net-metered capacity.
Small-scale solar in Mississippi produced an estimated 33 million kWh in 2025, 5th lowest among the states, from 21 MW6 of capacity. Home batteries are rare: utilities reported 111 residential batteries paired with net-metered solar, all of them at Southern Pine Electric Cooperative.
Source: Energy Information Administration, Small-scale solar photovoltaic generation and capacity estimates. EIA estimates for photovoltaic systems under 1 MW (homes and businesses), million kWh (GWh) a year.
Show the numbers
| Year | Million kWh |
|---|---|
| 2017 | 11 |
| 2018 | 11 |
| 2019 | 14 |
| 2020 | 15 |
| 2021 | 16 |
| 2022 | 22 |
| 2023 | 23 |
| 2024 | 30 |
| 2025 | 33 |
Incentives and tax credits for a Mississippi system
For Mississippi Power customers, part of the incentive is built into the export credit itself: the 2.5¢ per kWh Distributed Generation Value for every participant and the further 2.0¢ per kWh for households at or below 225% of the Federal Poverty Level, each for 25 years.2 It applies only to exported energy, not to the output a home uses itself.
The federal residential clean energy credit does not apply to expenditures made after December 31, 2025, and an expenditure is made when the original installation is completed, not when a contract is signed. A household whose installation was completed in 2025 and whose credit exceeded its tax for that year carries the unused part forward to the next tax year.7
Under a lease or power purchase agreement, the company that owns the system, not the household, may claim the §48E investment credit, and any benefit passed to the monthly payment depends on the contract. For solar whose construction begins after July 4, 2026, §48E does not apply to property placed in service after December 31, 2027.89 The federal solar tax credit page covers both credits and the dates in full.
Questions and answers
Does Mississippi have net metering?
Not in the retail kWh-for-kWh sense. Mississippi Power's Renewable Energy Net Metering Rate Schedule RENM-3 credits exports at the company's basic avoided energy cost plus a 2.5¢ per kWh Distributed Generation Value, which is net billing in everything but name.2
How does Mississippi Power net metering work?
Under RENM-3, effective May 27, 2025, the avoided energy cost rate for exported energy is adjusted upward by 2.5¢ per kWh for all participants, and the adder remains for 25 years from the date of installation. Low-to-moderate income customers at or below 225% of the Federal Poverty Level receive an additional 2.0¢ per kWh.2
How does Entergy Mississippi net metering work?
Entergy Mississippi reports the most residential net-metering installations in the state, but its terms are set in its own tariff, not in Mississippi Power's RENM-3. Entergy Mississippi customers should read the company's own schedule before relying on any rate.
How big can a home solar system be on Mississippi Power?
The lesser of 110% of the customer's annual peak demand or 20 kW for a residential customer; residential systems above 20 kW and up to 100 kW may use the company's Cogeneration and Small Power Production schedule instead.2
Does Mississippi have solar incentives in 2026?
Mississippi Power's export credit itself includes the 2.5¢ per kWh adder and the 2.0¢ low-to-moderate income adder.2 The federal residential clean energy credit does not apply to expenditures made after December 31, 2025, and an expenditure counts as made when installation is completed.7
Related to Mississippi
Sources
- Energy Information Administration, Form EIA-861 Annual Electric Power Industry Report, 2025 final data, Net_Metering_2025.xlsx (f8612025.zip), released October 7, 2026. eia.gov
- Mississippi Power, Renewable Energy Net Metering Rate Schedule RENM-3 (MPSC Schedule No. 59). Effective: 2025-05-27.
EFFECTIVE DATE May 27, 2025 ... adjusted upward to include the Distributed Generation Value, as defined in the MDGR, in the amount of 2.5 ¢/kWh for all participants. This 2.5 ¢/kWh adder will remain in place for twenty-five (25) years from the date of installation ... For customers qualifying as …
Checked November 16, 2026. mississippipower.com - Energy Information Administration, Electricity retail sales, residential average price, electricity/retail-sales, sector RES, released October 23, 2026. eia.gov
- Energy Information Administration, Form EIA-861M monthly net metering, 2026, net_metering2026.xlsx, released October 23, 2026. eia.gov
- Energy Information Administration, Form EIA-861 Annual Electric Power Industry Report, net metering 2010–2025, Net_Metering sheets of the annual files, released October 7, 2026. eia.gov
- Energy Information Administration, Small-scale solar photovoltaic generation and capacity estimates, Electric Power Monthly Table 1.1; small_scale_solar files, released October 23, 2026. eia.gov
- 26 U.S.C. §25D, Residential clean energy credit, Text current through Public Law 119-142 (November 10, 2026).
in the case of property placed in service after December 31, 2021, 30 percent … The credit allowed under this section shall not apply with respect to any expenditures made after December 31, 2025. … an expenditure with respect to an item shall be treated as made when the original installation of …
Checked November 16, 2026. uscode.house.gov - Public Law 119-21 (July 4, 2025), sections 70506 and 70513, 139 Stat. 72.
Section 25D(h) is amended by striking ``to property placed in service after December 31, 2034'' and inserting ``with respect to any expenditures made after December 31, 2025'' … shall apply to facilities the construction of which begins after the date which is 12 months after the date of enactment of this Act
Checked November 16, 2026. govinfo.gov - 26 U.S.C. §48E, Clean electricity investment credit, Text current through Public Law 119-142 (November 10, 2026).
with a maximum net output of less than 1 megawatt (as measured in alternating current) … This section shall not apply to any qualified property placed in service by the taxpayer after December 31, 2027, which is part of an applicable facility. … This paragraph shall not apply with respect to any …
Checked November 16, 2026. uscode.house.gov
Rules are quoted from the official text and dated; how we check them: methodology. Not legal or tax advice. Found an error? Write to [email protected]; corrections are listed on the updates page.