Net metering grandfathering: how long legacy solar tariffs last
Grandfathering lets solar customers who connected under an older tariff keep its crediting rules after new customers move to a successor, but only for a set period. The terms in force run from seven years for Hawaiian Electric's export rates to the life of the system in Illinois,1219 and the clock may start at permission to operate, at interconnection or at the application date. The next large transition is in North Carolina, where Duke Energy's legacy customers can stay on Rider NM until December 31, 2026 and then move automatically to the Net Metering Bridge rider.13
Published November 16, 2026. Rules checked November 16, 2026.
What grandfathering protects
When a legislature or commission replaces net metering, it normally closes the old tariff to new applicants and lets the customers already on it stay. Virginia wrote that protection into the statute that ordered its successor proceeding: "Nothing in the Commission's final order shall affect any eligible customer-generators ... who interconnect before the effective date of such final order."1
The protection is not automatic, and there is no single standard. Delaware changed how monthly excess credits are valued from January 1, 2024 "for existing and future net energy metering customers", so older systems moved to the new valuation along with new ones.2
Where legacy terms do exist, three details decide what they are worth to a particular home: how long they last, which event starts the clock, and whether they belong to the customer, the house or the equipment. Those details differ between states and sometimes between two riders at the same utility.
How long legacy terms last: fixed terms
Most legacy periods are a set number of years counted from an event in the system's life. The table lists the terms in the tariffs, statutes and orders we cite.
| Where | What is protected | How long | Counted from or tied to |
|---|---|---|---|
| California: PG&E, SCE, SDG&E | NEM 1.0 and NEM 2.0 net metering345 | 20 years | the date the customer first received permission to operate6 |
| California: SCE | Net Billing Tariff | nine years | the original permission-to-operate date7 |
| California: PG&E | Net Billing Tariff export values, applications through December 31, 2027 | nine-year schedule | the Avoided Cost Calculator in force on January 1 of the application year8 |
| Arizona: APS | Rider EPR-6 net metering | up to 20 years | interconnection910 |
| Arizona: APS and TEP | the customer's initial RCP export rate | 10 years | interconnection11 |
| Hawaii: Hawaiian Electric | SRE Export rates | first 7 years | a new interconnection agreement12 |
| North Carolina: Duke Energy | Rider NMB (Net Metering Bridge) | up to 15 years | the interconnection request application13 |
| New York: PSEG Long Island | Phase One net metering | 20 years | the project's in-service date14 |
| Iowa | the retail volumetric rate for outflow, for facilities that start before a value of solar rate is approved | a term of twenty years | the facility's years of operation15 |
| Kentucky | the 1:1 kWh credit, for systems in service before the utility's first order under KRS 278.466(3) | 25 years | the premises, whether or not they are sold16 |
| Massachusetts | retail-based Net Metering Credits for solar | 25 years | the date the facility was first authorized to interconnect17 |
| Mississippi Power | the 2.5¢ per kWh distributed generation adder | 25 years | installation18 |
| Illinois: ComEd, Ameren | full retail net metering, systems interconnected before January 1, 2025 without a DG rebate | life of the system | interconnection19 |
The shortest terms in the table protect an export rate (APS, TEP, Hawaiian Electric, California's net billing values) or a bridge rider rather than full 1:1 net metering. A customer on one of them is already on a successor design; the lock holds the rate in place for a while, and then the customer moves to whatever applies at the time.
NEM 2.0 grandfathering in California
California's Net Billing Tariff, adopted in Decision 22-12-056, applies to customers who submitted an interconnection application on or after April 15, 2023.20 Customers already on NEM 1.0 or NEM 2.0 stay there. PG&E's NEM2 schedule lets them continue "for a period of 20 years from the original year in which their Generating Facility was interconnected", measured from the date the customer originally received permission to operate (PTO), and then moves them to the Net Billing Tariff.6
The clock starts at the PTO date, not at the contract signature or the end of installation, and the schedule keeps the customer on NEM 2.0 to the end of the tariff's "Relevant Period" that follows the 20th anniversary of that date.6
Net billing customers have a shorter lock of their own. SCE keeps a Net Billing Tariff customer on the tariff for nine years from the original PTO date; the tariff's own example runs a May 31, 2023 PTO through the Relevant Period ending on or after May 31, 2032.7 PG&E fixes a nine-year schedule of hourly export values for complete applications submitted from April 15, 2023 through December 31, 2027, taken from the Avoided Cost Calculator adopted as of January 1 of the application year.8
The ACC Plus adder, an extra credit per exported kWh for early net billing customers, also stays constant for nine years from PTO, and it shrinks for each later year of applications. PG&E's tariff does not give it to NEM and NEM2 customers who move to net billing at the end of their legacy period.8 The California net billing tariff page shows the values by year.
The APS grandfather date, and TEP's
APS has two clocks, and neither is a single calendar date. Residential customers on its frozen net metering rider, Rider EPR-6, "may remain on this rate rider for up to 20 years from the date their solar generator was interconnected".910 APS's own solar transition page explains that in 2017 the Arizona Corporation Commission changed how excess energy sent to the grid is credited, and that "your current solar buyback rate lasts 20 years from the date your system was connected to the APS grid."21
Under EPR-6, export energy that has not been netted on a bill by the December billing cycle is bought at $0.02895 per kWh.910 That is the rate in the rider's current revision, effective March 8, 2024.
Customers who connected after the 2017 change are on Rider RCP, where the clock protects a rate rather than net metering. Each customer's initial RCP rate applies for 10 years from interconnection. APS sets a new rate for each annual tranche from September 1, and the rate may not be reduced by more than 10% a year.10 The 2026 tranche, September 1, 2026 through August 31, 2027, is $0.05554 per kWh; the 2017 tranche was $0.12900.9 A household's tranche, fixed when it connects, sets its credit for the decade. The APS page runs the same home through two tranches.
Tucson Electric Power uses the same design under Rider R-14: the initial RCP rate is held for 10 years from interconnection, and the rider "may not be used in conjunction with the grandfathered net metering rate rider, TEP Rider-4".11 A customer cannot be on both. TEP's rate for applications from October 1, 2026 is $0.0462 per kWh.22
Legacy tariffs with a calendar end date
Some states end the old tariff on one date for everyone on it, whenever they connected. Rocky Mountain Power's Utah net metering schedule, Schedule 135, closed to applications for new service as of November 15, 2017, and "Service under this Schedule will terminate on December 31, 2035."23 A Utah system connected in 2010 and one connected in 2017 leave the schedule on the same day.
| Date | Where | What changed |
|---|---|---|
| December 31, 2026 | North Carolina | Legacy Duke net metering customers move to the Net Metering Bridge. Residential customers still on Rider NM are moved automatically to Rider NMB.1324 |
| January 1, 2027 | North Carolina | Duke Energy Progress closes the Net Metering Bridge to new participants. Rider NMB closes to new participants on January 1, 2027; those who applied before then keep it for up to 15 calendar years from their interconnection application.25 |
| January 1, 2027 | New Hampshire | New Hampshire rule on exports from storage takes effect. Paragraph XXV of RSA 362-A:9, on exports from storage, takes effect January 1, 2027.2627 |
| January 1, 2027 | Colorado | Colorado HOA rules can no longer bar portable-scale solar. Under HB 26-1007, homeowners association restrictions cannot bar portable-scale solar generation devices on and after January 1, 2027.28 |
| February 1, 2027 | Maryland | Deadline for Maryland’s successor to net metering. The PSC must approve a successor framework, to begin July 1, 2027.29 |
| July 1, 2027 | Maryland | Maryland’s current net metering closes. The standard tariff is offered until the earlier of 3,000 MW statewide or July 1, 2027.3031 |
| July 1, 2027 | Kansas | Kansas net metering availability limit rises to 5%. The first-come, first-served limit becomes 5% of the utility’s historic highest annual peak since 2014; from July 1, 2026 it was 4% of the prior year’s peak.32 |
| December 31, 2027 | California | Last day to apply for California net billing with a nine-year lock. PG&E’s tariff locks nine years of export values for applications submitted through December 31, 2027.8 |
| December 31, 2027 | Federal | Placed-in-service deadline for later-started third-party solar. Section 48E does not apply to solar property placed in service after December 31, 2027 unless construction began by July 4, 2026.3334 |
| April 1, 2028 | Idaho | Idaho Power’s next export credit update filing. Annual updates are suspended until this filing under Order No. 36785.35 |
| May 31, 2029 | South Carolina | South Carolina legacy net metering ends. Customers who applied before June 1, 2021 may continue net energy metering until May 31, 2029.36 |
| June 30, 2029 | Washington | Washington’s mandatory net metering offer may end. Utilities must offer net metering until the earlier of June 30, 2029 or a capacity threshold.37 |
| January 1, 2030 | Kansas | Pre-2014 Kansas net metering customers lose kWh rollover. Rollover and transferability for customers from before July 1, 2014 end on January 1, 2030.3238 |
| December 31, 2035 | Utah | Utah legacy net metering ends. Service under Rocky Mountain Power Schedule 135 terminates.23 |
| June 1, 2040 | Arkansas | Entergy Arkansas legacy net metering ends. Legacy terms apply until June 1, 2040.3940 |
| December 20, 2045 | Idaho | Idaho Power legacy net metering ends. Legacy systems stay on monthly net metering until legacy status terminates on December 20, 2045.41 |
| July 1, 2047 | Indiana | Indiana pre-2018 net metering ends. Systems installed before January 1, 2018 stay on net metering until removal or July 1, 2047, whichever is earlier.42 |
The dates in the table come from the instruments themselves. Entergy Arkansas's legacy schedule applies "until June 1, 2040, to Net-Metering Facilities of Legacy Net-Metering Customers".3940 Idaho Power's legacy systems stay on monthly net metering "until legacy status terminates on December 20, 2045".41 In Kansas, customers from before July 1, 2014 keep kWh rollover and transferability until January 1, 2030.3238
Is net metering going away? For customers who already have it, legacy terms either last for a stated period or end on a published date, and some run past 2040. Hawaiian Electric's NEM and NEM+ customers are not required to transition at all.4344 For new customers it is closing in more places. Maryland's current net metering is offered until the earlier of 3,000 MW statewide or July 1, 2027,30 and Washington's utilities must offer it only until the earlier of June 30, 2029 or a capacity threshold.37 The change log tracks each date with its source.
North Carolina: the transition on December 31, 2026
Duke Energy's North Carolina customers are the first large group to reach the end of a legacy period. Residential Rider NM closed to new customers as of September 30, 2023, and the Residential Solar Choice (Rider RSC) and Net Metering Bridge (Rider NMB) riders took effect October 1, 2023. Residential customers with existing net-metered systems can stay on Rider NM until December 31, 2026, "at which point they will be automatically transitioned to Rider NMB."13
Rider NMB is open to a limited number of customers each year, and customers can stay on it for up to 15 years from the date of their interconnection request application. Under the revised riders, excess energy exported each month is credited at the Net Excess Energy Credit (NEEC) rate, based on the utility's avoided costs, and the fixed customer charge and the REPS charge cannot be offset by net metering credits.13
Duke Energy reported 54,31345 residential net-metering installations in North Carolina at the end of 2025. EIA does not split that count by rider, so it covers both legacy Rider NM accounts and homes already on the newer riders. The North Carolina page works through a month on a Duke bill under the newer riders.
Tied to the customer, the house or the equipment
Who owns the protection matters most when a house is sold. The rules point in different directions.
- The customer. California's net billing decision says: "The legacy period is linked to the customer who originally causes the system to be installed, not to the system."345 Under that wording, a later buyer of the home is not that customer.
- The premises. Kentucky keeps the 1:1 kWh credit "for a twenty-five (25) year period, regardless of whether the premises are sold".16 ComEd says systems eligible for a legacy rate on December 31, 2024 "shall maintain eligibility for the lifetime of the system, with subsequent customers inheriting such eligibility."46
- The application, including later owners. South Carolina lets customer-generators who applied before June 1, 2021, "including subsequent owners", continue net energy metering under Order No. 2015-194 until May 31, 2029.36
- The equipment. Indiana's statute keeps a customer whose system was installed before January 1, 2018 on net metering until the customer removes or replaces the net metering facility, or July 1, 2047, whichever comes first.42
A buyer who wants to know which rule applies needs the seller's interconnection date, the tariff or rider on the bill, and the utility's written answer on transfer. Our guide to reading a net metering bill shows where the rider name appears.
Upgrades, batteries and expansions
Legacy status usually covers the system as approved. Illinois protects full retail net metering for systems interconnected before January 1, 2025 "for the life of the system unless material modifications are made."19
Idaho Power lists what counts as a modification: "adding or replacing solar panels or generation equipment, inverter replacements, or adding batteries." Each must go through the interconnection process again, including a new application.47 For Idaho Power's legacy customers, that turns a battery or a replacement inverter into a utility review of the system that carries the legacy status.
APS's Rider RCP draws its own line for expansions: it defines a material increase in capacity as "increasing the capacity by 10% or 1 kW-ac, whichever is greater".910 Long Island is more permissive about storage: PSEG Long Island's tariff lets mass-market projects on net metering pair on-site energy storage "and remain eligible under Phase One NEM."14
Contracts can also be closed to extension. Maine bars any amendment, revision or reissuance of a net energy billing agreement made after June 1, 2025 from setting a delivery period end date later than the one in the agreement.48 In Hawaii, Customer Grid-Supply, Customer Grid-Supply Plus and Smart Export customers move to Smart Renewable Energy Export 7 years after their initial contract date, a rule in place from October 1, 2024, while the older NEM and NEM+ customers are not required to transition.124344
What a legacy tariff does not freeze
Grandfathering keeps the crediting method; it does not freeze the bill. PG&E's NEM2 customers "must pay the non-bypassable charges ... in each metered interval for each kilowatt-hour of electricity they consume from the grid."6 Under 1:1 net metering the value of each credit also follows the retail rate, so a legacy credit is worth more or less as rates change.
Vermont shows both sides. Its 2026 biennial update raised the statewide blended residential rate, the base value of the bill credit for "all applicable net-metering systems, both existing and proposed", to $0.2071 per kWh from August 1, 2026, while "the biennial update process does not change the value of siting adjustors that apply to existing systems."49
New York's Customer Benefit Contribution, a monthly charge per kW-DC of panels, does not apply to customers who interconnected solar before January 1, 2022. For those who pay it, "CBC rates change annually and customers do not lock in a rate."50
When the term ends, the account moves on. At PSEG Long Island, at the end of the billing period containing the 20th anniversary of a project's in-service date, the utility removes any remaining excess credits and the project moves to the successor compensation.14 In Massachusetts, a solar facility receives the lower Market Net Metering Credits after 25 years from the date it was first authorized to interconnect.17
Grandfathering and the federal tax credit
Staying on NEM 2.0 or an early RCP tranche does not keep a tax credit alive. The homeowner credit covers only expenditures made by December 31, 2025, and the statute dates an expenditure by the completion of the original installation, so an expansion or battery added to a legacy system in 2026 earns no §25D credit. What a legacy household may still have is unused credit from its original installation, which carries forward year to year.51 A leased legacy system is the owner's tax matter under §48E, not the homeowner's.33 The leases and PPAs page explains the owner's credit. This is not tax advice.
Questions and answers
What does it mean to be grandfathered on net metering?
It means your account stays on the tariff that applied when your system was approved, even after the utility closes that tariff to new customers. The protection has an end: in California it lasts 20 years from the date the customer first received permission to operate, after which the account moves to the current tariff.6
How long is NEM 2.0 grandfathered?
For 20 years from the date the customer originally received permission to operate (PTO), held under PG&E's NEM2 schedule to the end of the tariff's "Relevant Period" after the 20th anniversary; the account then moves to the Net Billing Tariff.6
What is the APS net metering grandfather date?
There is no single date. A residential customer on APS's frozen net metering rider, EPR-6, may stay on it for up to 20 years from the date the solar system was interconnected, and a customer on Rider RCP keeps the initial export rate for 10 years from interconnection.910
Is net metering going away for people who already have it?
Not overnight, but several legacy tariffs have fixed end dates. Rocky Mountain Power's Utah Schedule 135 terminates on December 31, 2035,23 and South Carolina customers who applied before June 1, 2021 may continue net energy metering until May 31, 2029.36
Does grandfathered net metering transfer when I sell my house?
It depends on the state. Kentucky keeps the 1:1 kWh credit at the premises for 25 years regardless of whether they are sold,16 and ComEd says later customers at the premises inherit legacy eligibility.46 California's Net Billing Tariff ties its legacy period to the customer who had the system installed, not to the system.345
Related guides
Sources
- Va. Code §56-594 Net energy metering provisions (both versions: until and from Jan 1, 2027).
(i) has a capacity of not more than 25 kilowatts for residential customers and not more than three megawatts for nonresidential customers ... "Net metering period" means the 12-month period following the date of final interconnection ... until the rated generating capacity ... reaches six percent, …
Checked November 16, 2026. law.lis.virginia.gov - 26 Del. C. ch. 10 (§1014 net metering provisions). Effective: 2024-01-01.
Provide for customers to be credited in kilowatt-hours (kWh) for any excess production ... Excess kWh Credits at the end of an annualized billing period shall carry over to subsequent annualized billing periods. ... b. Effective January 1, 2024, for commission-regulated utilities for existing and …
Checked November 16, 2026. delcode.delaware.gov - CPUC, Net Energy Metering and Net Billing - Key Information. Effective: 2023-04-15.
Since April 15, 2023, customers applying for interconnection have taken service on the new net billing tariff (NBT) pursuant to D.22-12-056 . ... The IOUs refer to the NBT as the “Solar Billing Plan.” ... Pursuant to D.14-03-041 , customer-generators are allowed to remain on the NEM 2.0 tariff for …
Checked November 16, 2026. cpuc.ca.gov - CPUC Decision 22-12-056 (R.20-08-020), Ordering Paragraph 1. Effective: Decision 2022-12-15; tariff 2023-04-15.
A net billing tariff is adopted. Imports and exports will be calculated based on no netting of consumption and production and will be trued-up on an annual basis. ... The ACC Plus will be available to net billing tariff customers during the first five years of the successor tariff, as a glide path. …
Checked November 16, 2026. docs.cpuc.ca.gov - Senate Energy, Utilities & Communications Committee analysis of AB 942 (hearing 7/15/2025). Effective: pending/unknown.
This bill modifies the terms applicable to customer-generators participating in the Net Energy Metering (NEM) tariff, including by requiring customer-generators of electrical corporations to be transferred to a new tariff when the property has been sold
Checked November 16, 2026. seuc.senate.ca.gov - PG&E Electric Schedule NEM2 – Net Energy Metering Service, Cal. P.U.C. Sheet 59228-E (Sheet 46) et seq.; CPUC D.16-01-044.
are eligible to continue receiving service on this NEM2 Schedule for a period of 20 years from the original year in which their Generating Facility was interconnected to PG&E’s grid, indicated by and measured from the date on which the Customer originally received Permission To Operate (PTO) … …
Checked November 16, 2026. pge.com - SCE Schedule NBT – Net Billing Tariff, Cal. PUC Sheets 85375-E et seq. (e.g., Sheet 30 = 87700-E); Advice 4961-E/4961-E-A (eff. 2023-03-01), 5170-E-A (eff. 2023-12-14), 5228-E (eff. 2024-02-15), 5533-E (eff. 2025-04-23); D.22-12-056; D.23-11-068.
Residential Customers taking service under this Schedule must be on the Prime Option of Schedule TOU-D. … multiplying the hourly-differentiated Customer’s Energy Export (channel 2) in kWh by the applicable Energy Export Credit Price (EEC Price), as defined below, derived from the approved Avoided …
Checked November 16, 2026. sce.com - PG&E Electric Schedule NBT – Net Billing Tariff (NBT) Service, Cal. P.U.C. Sheets 55440-E et seq.; Advice 6848-E (eff. 2023-03-01), Advice 7174-E (eff. 2024-02-15); CPUC D.22-12-056, D.23-11-068.
The NBT schedule may also be referred to as the Solar Billing Plan in customer-facing communications. Residential customers, including Load Aggregation Generating/Aggregated Accounts, taking service on NBT must take service on the E-ELEC (ELECTRIC HOME) rate schedule … For both residential and …
Checked November 16, 2026. pge.com - APS Rate Rider RCP – Partial Requirements Service for New On-Site Solar DG, Resource Comparison Proxy Export Rate, A.C.C. No. 6248, Revision No. 11, effective September 1, 2026 in ACC Decision No. 82122.
The Company will meter this Export Energy on an instantaneous basis and provide a monthly bill credit based on the purchase rate in this schedule. … Tranche 2025 September 1, 2025 through August 31, 2026 $0.06171 per kWh Tranche 2026 September 1, 2026 through August 31, 2027 $0.05554 per kWh … An …
Checked November 16, 2026. aps.com - APS Rate Rider EPR-6 Legacy (Frozen) – Net Metering, A.C.C. No. 6194, Revision No. 2, effective March 8, 2024 in Decision No. 79293.
Each Customer’s initial RCP rate will be applicable for 10 years from the time of their interconnection. ... A residential Customer may remain on this rate rider for up to 20 years from the date their solar generator was interconnected … After the December billing cycle, any export energy that has …
Checked November 16, 2026. aps.com - TEP Rider R-14, Resource Comparison Proxy Export Rate (RCP-PRS), Sheet No. 714, Original Sheet 714-0/714-1, effective September 1, 2023, ACC Decision No. 79065.
The Company will meter this export power on an instantaneous basis and provide a monthly bill credit based on the purchase rate in this schedule. ... 3. Each Customer’s initial RCP rate will be applicable for 10 years from the time of their interconnection. … Each calendar year, for the customer …
Checked November 16, 2026. docs.tep.com - Hawaiian Electric – Smart Renewable Energy Export program page, Hawaiian Electric web page, checked 2026-11-16.
Smart Renewable Energy (SRE) - Export rates for 2024-2026 Island Overnight (9pm - 9am) Daytime (9am - 5pm) Evening Peak (5pm - 9pm) Oahu 18.9 cents/kWh* 13.5 cents/kWh* 32.9 cents/kWh* Maui 13.1 cents/kWh* 6.6 cents/kWh* 18.2 cents/kWh* … Export credits will be trued-up on an annual basis and any …
Checked November 16, 2026. hawaiianelectric.com - NC Public Staff – Net Metering (summary of NCUC Order Approving Revised Net Metering Tariffs, Docket E-100, Sub 180, March 23, 2023, and Order Granting Extension of Time, May 17, 2023), NCUC Docket No. E-100, Sub 180.
The current residential net metering rider (Rider NM) is closed to new customers as of September 30, 2023. The revised Net Metering riders (Residential Solar Choice (Rider RSC) and Net Metering Bridge (Rider NMB)) are effective October 1, 2023 for residential customers. … the excess energy you …
Checked November 16, 2026. publicstaff.nc.gov - LIPA Tariff for Electric Service (June 2026 compiled PDF), Net Metering, Section I.C.15.h — Leaf 34F-1 (Sixth Revised, eff. June 1, 2024) and Leaf 34F-2 (Third Revised, eff. April 1, 2023).
For Mass Market Projects and Commercial Demand NEM Projects served under a rate code with multiple rate periods, peak and off-peak periods will be treated separately when calculating and applying any credits. … In the event that the amount of electricity provided to the Authority by an eligible …
Checked November 16, 2026. lipower.org - Iowa Code 2026, §476.49 Distributed generation facilities - billing. Effective: 2020 Acts ch 1004; Iowa Code 2026.
(2) Any excess kilowatt-hours remaining at the end of a twelve-month period shall be cashed out at the electric utility’s avoided cost rate with the funds from the cash out divided evenly between the customer and the electric utility’s low-income home energy assistance program. ... (5) Prior to the …
Checked November 16, 2026. legis.iowa.gov - Kentucky PSC Order, Case No. 2023-00413 (Duke Energy Kentucky), 2024-10-11. Effective: SB 100 (2019); order 2024-10-11.
Pursuant to KRS 278.466(3), customers taking service under Rider NM -2 will be compensated for electricity fed into the grid over a billing period at a rate set by the Commission using ratemaking processes ... KRS 278.466(4) provides that compensation: [S]hall be in the form of a dollar-denominated …
Checked November 16, 2026. psc.ky.gov - 220 CMR 18.04 Calculation of Net Metering Credits (via Cornell LII).
each Distribution Company shall calculate for each Billing Period a Net Metering Credit equal to: (a) 100% of the net excess kilowatt-hours, by time of use, if applicable, multiplied by the sum of the following Distribution Company charges ...: 1. basic service kilowatt-hour charge ... 2. …
Checked November 16, 2026. law.cornell.edu - Mississippi Power, Renewable Energy Net Metering Rate Schedule RENM-3 (MPSC Schedule No. 59). Effective: 2025-05-27.
EFFECTIVE DATE May 27, 2025 ... adjusted upward to include the Distributed Generation Value, as defined in the MDGR, in the amount of 2.5 ¢/kWh for all participants. This 2.5 ¢/kWh adder will remain in place for twenty-five (25) years from the date of installation ... For customers qualifying as …
Checked November 16, 2026. mississippipower.com - Illinois Shines (Illinois Power Agency), FAQs Related to Changes in Net Metering in Illinois - Consumers (26 July 2024). Effective: 2025-01-01.
Under Illinois law, customers beginning net metering service on or after January 1, 2025 will receive net metering just for supply charges, rather than the full retail rate net metering. ... Residential and small commercial customers interconnected to Ameren or ComEd prior to January 1, 2025 who …
Checked November 16, 2026. illinoisshines.com - CPUC – Net Billing Tariff page, CPUC web page.
On December 15, 2022, the CPUC adopted D.22-12-056, establishing the Net Billing tariff (NBT) as a successor to NEM2. ... The NBT will apply to customers who submit an interconnection application on or after April 15, 2023.
Checked November 16, 2026. cpuc.ca.gov - APS, Solar Energy Credit Transition. Effective: 2017 (ACC Decision No. 75859, Docket E-00000J-14-0023).
In 2017, the Arizona Corporation Commission changed how customers are credited for excess energy sent to the grid from rooftop solar systems. ... Your current solar buyback rate lasts 20 years from the date your system was connected to the APS grid.
Checked November 16, 2026. aps.com - TEP Statement of Charges (Sheet 801 series), Rider R-14 RCP rate history with ACC Decision numbers; Oct 1, 2026 rate per Decision No. 82172.
Rider R-14 – Resource Comparison Proxy (RCP) $0.0964 per kWh $0.0868 per kWh $0.0868 per kWh $0.0781 per kWh $0.0703 per kWh $0.0633 per kWh $0.0570 per kWh $0.0513 per kWh $0.0462 per kWh September 21, 2018 October 1, 2019 October 1, 2020 October 1, 2021 October 1, 2022 October 1, 2023 October 1, …
Checked November 16, 2026. docs.tep.com - Rocky Mountain Power Utah Schedule No. 135 Net Metering Service. Effective: Docket 14-035-114 order 2017-09-29.
Net Metering Service Closed to Applications for New Service as of November 15, 2017 ... with a capacity of not more than twenty-five (25) kilowatts for a residential facility and two (2) megawatts for a non[-residential] ... TERM: Service under this Schedule will terminate on December 31, 2035.
Checked November 16, 2026. rockymountainpower.net - NC Utilities Commission Public Staff, Net Metering. Effective: 2023-10-01.
On March 23, 2023, in Docket No. E-100, Sub 180 , the Commission issued its Order Approving Revised Net Metering Tariffs ... The current residential net metering rider (Rider NM) is closed to new customers as of September 30, 2023. The revised Net Metering riders (Residential Solar Choice (Rider …
Checked November 16, 2026. publicstaff.nc.gov - Duke Energy Progress, Net Metering Bridge Rider NMB, NC Fourth Revised Leaf No. 605, effective April 1, 2026; NCUC Docket No. E-2, Sub 1396.
This Rider will be closed to new participants on and after January 1, 2027. ... shall remain eligible for service under this Rider for up to 15 calendar years from the submission date of the applicable interconnection application ... 2026 43,500
Checked November 16, 2026. duke-energy.com - RSA 362-A:9, Net Energy Metering (New Hampshire General Court).
XV. Standard tariffs that are available to eligible customer-generators under this section shall terminate on December 31, 2040 and such customer-generators shall transition to tariffs that are in effect at that time. ... may elect to receive a payment from the distribution utility either on an …
Checked November 16, 2026. gc.nh.gov - NH PUC Order No. 27,074, Docket DE 22-060, Order on Net Metering (November 18, 2024). Effective: November 18, 2024.
Retain the existing compensation levels for all net-metered customer- generators in the Alternative Net Energy Metering Tariff approved in Order No. 26,029 (NEM 2.0); ... receive compensation for each exported kWh of electricity at a rate of 100 percent of the default service (energy) charge, 100 …
Checked November 16, 2026. puc.nh.gov - Colorado Session Laws 2026, Ch. 127, House Bill 26-1007. Effective: ~2026-08-12 (90 days after adjournment).
(1.3) ON OR BEFORE DECEMBER 31, 2026, THE COMMISSION SHALL REVISE EXISTING RULES TO: (a) REQUIRE A QUALIFYING RETAIL UTILITY TO POST AND MAINTAIN ON ITS WEBSITE A PUBLIC LIST OF AT LEAST ONE METER COLLAR ADAPTER ... (VII) ON AND AFTER JANUARY 1, 2027, A PORTABLE-SCALE SOLAR GENERATION DEVICE, AS …
Checked November 16, 2026. leg.colorado.gov - Md. Code, Public Utilities §7-306.4. Effective: successor to begin 2027-07-01.
(c) On or before February 1, 2027, the Commission, by order or regulation, shall approve, as a successor program to the net energy metering program under § 7–306 of this subtitle, a framework for a net energy metering program to begin July 1, 2027, that: (1) provides incentives for the development …
Checked November 16, 2026. mgaleg.maryland.gov - Md. Code, Public Utilities §7-306.
on a first–come, first–served basis until the earlier of: (i) the date on which the rated generating capacity owned and operated by eligible customer–generators in the State reaches 3,000 megawatts; or (ii) July 1, 2027. ... the dollar value of net excess generation shall be equal to the generation …
Checked November 16, 2026. mgaleg.maryland.gov - Md. Code Ann., Public Utilities § 7-306 (Maryland General Assembly statute text), PUA § 7-306 (current text as served 2026-11-16).
make it available to eligible customer–generators on a first–come, first–served basis until the earlier of: (i) the date on which the rated generating capacity owned and operated by eligible customer–generators in the State reaches 3,000 megawatts; or (ii) July 1, 2027. … “Net excess generation” …
Checked November 16, 2026. mgaleg.maryland.gov - K.S.A. 66-1265 Utility requirements. Effective: 2024-07-01.
make net metering available to customer-generators ... until the total rated generating capacity ... equals: (A) Commencing July 1, 2024, 2% of the utility's peak demand during the previous year; (B) commencing July 1, 2025, 3% ...; (C) commencing July 1, 2026, 4% ...; and (D) commencing July 1, …
Checked November 16, 2026. ksrevisor.gov - 26 U.S.C. §48E, Clean electricity investment credit, Text current through Public Law 119-142 (November 10, 2026).
with a maximum net output of less than 1 megawatt (as measured in alternating current) … This section shall not apply to any qualified property placed in service by the taxpayer after December 31, 2027, which is part of an applicable facility. … This paragraph shall not apply with respect to any …
Checked November 16, 2026. uscode.house.gov - Public Law 119-21 (July 4, 2025), sections 70506 and 70513, 139 Stat. 72.
Section 25D(h) is amended by striking ``to property placed in service after December 31, 2034'' and inserting ``with respect to any expenditures made after December 31, 2025'' … shall apply to facilities the construction of which begins after the date which is 12 months after the date of enactment of this Act
Checked November 16, 2026. govinfo.gov - Idaho PUC Final Order No. 36785, Case No. IPC-E-25-15 (service date Sept 30, 2025), Order No. 36785; builds on Order No. 36048 (Case IPC-E-23-14).
The Company stated the Order approved changes to its on-site generation service offerings including implementing, effective January 1, 2024, a seasonal and time-variant ECR with avoided cost-based value considerations for excess energy exported to the C[ompany] … an ECR update where the change in …
Checked November 16, 2026. puc.idaho.gov - S.C. Code §58-40-20 Net energy metering; solar choice metering. Effective: 2019-05-16; amended 2025-05-12.
(B) An electrical utility shall make net energy metering available to all customer-generators who apply before June 1, 2021, according to the terms and conditions provided to all parties in Commission Order No. 2015-194. Customer-generators who apply for net metering after the effective date of …
Checked November 16, 2026. scstatehouse.gov - RCW 80.60.020.
(a) Shall offer to make net metering, pursuant to RCW 80.60.030 , available to eligible customer-generators on a first-come, first-served basis until the earlier of either: (i) June 30, 2029; or (ii) the first date upon which the cumulative generating capacity of net metering systems equals four …
Checked November 16, 2026. app.leg.wa.gov - K.S.A. 66-1266 Interconnection agreements; billing; credit for exports. Effective: 2024-07-01.
(b) For any customer-generator that began operating ... on and after July 1, 2014: ... all such net excess generation remaining in such customer-generator's account at the end of each billing period shall be credited to the customer at a rate of at least 100% of the utility's monthly system average …
Checked November 16, 2026. ksrevisor.gov - Entergy Arkansas Rate Schedule No. 52 Legacy Net-Metering Service (LN-M), APSC Docket 23-070-TF. Effective: 2023-12-31.
52.3.1. The monthly billing rate structure, terms, and conditions outlined herein apply until June 1, 2040, to Net-Metering Facilities of Legacy Net-Metering Customers. ... 52.3.5. ... the Company shall credit the Legacy Net- Metering Customer with any accumulated Net Excess Generation in the next …
Checked November 16, 2026. entergyarkansas.com - Act 278 of 2023 (SB 295), Arkansas General Assembly, Customer Protections for Net-Metering Customers Act. Effective: 2023-03-13.
(C) By December 31, 2023, a commission shall approve modifications to each electric utility's rate schedules applicable to net-metering customers pursuant to the rate structure the electric utility elects under § 23-18-606(a) ... (11)(A) Allow a net-metering facility of an individual net-metering …
Checked November 16, 2026. arkleg.state.ar.us - Idaho PUC Staff Comments, Case IPC-E-23-14 (2023-10-12). Effective: 2024-01-01 (Order No. 36048).
Customers with legacy systems will continue to take service under the rules of monthlyNEM until legacy status terminates on December 20, 2045, also known as Grandfather Status. ... The Company is proposing a real-time net billing with an avoided cost-based financial credit rate for exported energy.
Checked November 16, 2026. puc.idaho.gov - IURC Technical Conference handout reproducing IC 8-1-40 (P.L. 264-2017) (2017-07-20). Effective: P.L. 264-2017; EDG from 2022-07-01 at latest.
equals the product of: (1) the average marginal price of electricity paid by the electricity supplier during the most recent calendar year; multiplied by (2) one and twenty-five hundredths (1.25). ... IC 8-1-40-18 ... Any excess credit shall be carried forward and applied against fu[ture charges] …
Checked November 16, 2026. secure.in.gov - Hawaiian Electric, Smart Renewable Energy Export. Effective: 2024-2026 rate period.
Export Rates will be updated every 3 years. ... There is no capacity limit for this program ... System size limit will be governed by Rule 14H. ... Starting on Oct. 1, 2024, Customer Grid-Supply, Customer Grid-Supply Plus and Smart Export will be transitioned to the Smart Renewable Energy Export …
Checked November 16, 2026. hawaiianelectric.com - Hawaiian Electric, Smart Renewable Energy Programs.
Net Energy Metering (NEM) and Net Energy Metering Plus (NEM+) customers are not required to transition to the new Smart Renewable Energy programs.
Checked November 16, 2026. hawaiianelectric.com - Energy Information Administration, Form EIA-861 Annual Electric Power Industry Report, 2025 final data, Net_Metering_2025.xlsx (f8612025.zip), released October 7, 2026. eia.gov
- ComEd, "2025 Changes to Net Metering" (062024), ComEd customer document, 2024; implements CEJA (P.A. 102-0662).
Full retail rate net metering will no longer be available to customers interconnecting renewable energy systems after December 31, 2024. Customers receiving permission to operate after such date will be eligible to receive only energy supply credits for their excess energy sent back to the grid. … …
Checked November 16, 2026. azure-na-assets.contentstack.com - Idaho Power, "Important Reminder For Your Renewable Energy System 2026" (customer generation brochure, 31180-I-0391), Idaho Power brochure (2026).
Export Credit Rate Summer On-Peak ..... 15.6836 per kilowatt-hour (kWh) Off-Peak ..... 3.3920 per kWh Non-Summer On-Peak ..... N/A Off-Peak ..... 2.9019 per kWh ... These rates are effective as of Oct. 1, 2025. … A Net Billing customer shall receive a credit for Exported Energy at the applicable …
Checked November 16, 2026. docs.idahopower.com - 35-A M.R.S. §3209-A Net energy billing (Maine Revisor, data extracted 10/05/2026).
taking into account accumulated unused kilowatt‑hour credits from the previous billing period. ... 2-A. Billing term length. An amendment, revision or reissuance of a net energy billing agreement made after June 1, 2025 may not include a delivery period end date that is later than the end date …
Checked November 16, 2026. legislature.maine.gov - Vermont PUC, 2026 Biennial Update of the Net-Metering Program, Order, Case No. 26-0291-INV (2026-05-29). Effective: 2026-08-01.
(1) The statewide blended residential rate, which is the base value of the bill credit offered to all applicable net-metering systems, both existing and proposed, is increased to $0.2071/kWh (an increase of $0.0231). ... (3) The siting adjustor for new Category I and II systems is reduced by $0.01 …
Checked November 16, 2026. puc.vermont.gov - NYSERDA, Utility-Published 2026 Customer Benefit Contribution Rates (NYSERDA document SUN-RSC-cbc-fs-1-v8, April 2026). Effective: 2026.
Residential and small commercial customers who interconnect solar PV at their site on or after January 1, 2022 will be subject to a new Customer Benefit Contribution (CBC) billing item ... The CBC is calculated based on a project’s DC system size and will not apply to customers who interconnected …
Checked November 16, 2026. nyserda.ny.gov - 26 U.S.C. §25D, Residential clean energy credit, Text current through Public Law 119-142 (November 10, 2026).
in the case of property placed in service after December 31, 2021, 30 percent … The credit allowed under this section shall not apply with respect to any expenditures made after December 31, 2025. … an expenditure with respect to an item shall be treated as made when the original installation of …
Checked November 16, 2026. uscode.house.gov
Rules are quoted from the official text and dated; how we check them: methodology. Not legal or tax advice. Found an error? Write to [email protected]; corrections are listed on the updates page.