Solar interconnection: the agreement, the review and permission to operate

Interconnection is the utility's approval to connect a home solar system to its grid, and permission to operate (PTO) is the final go-ahead to switch it on. The dates in that process matter beyond paperwork: at PG&E, the year of a complete interconnection application fixes the export values a Solar Billing Plan customer gets for nine years, for applications through December 31, 2027.6

Published November 16, 2026. Rules checked November 16, 2026.

What interconnection and permission to operate are

A rooftop solar system that sends power into the grid needs the utility's consent before it runs. That consent is interconnection: the customer (usually through the installer) applies, the utility reviews whether the system and the local wires can take it, the parties sign an interconnection agreement, and the utility confirms the meter and equipment before it grants permission to operate.

The rules for that process sit in a tariff or a commission rule, not in the net metering law alone. In California the governing document is Electric Rule 21, a CPUC-approved tariff that describes the interconnection, operating and metering requirements for generating facilities connected to an investor-owned utility's distribution system.1 Florida's Public Service Commission puts interconnection and net metering in one rule, Rule 25-6.065, "Interconnection and Net Metering of Customer-Owned Renewable Generation".2 Hawaiian Electric reviews system size under its Rule 14H interconnection rules.3

Because these documents belong to the investor-owned utilities, customers of municipal utilities and electric co-operatives apply under their own utility's rules. Rule 21, for instance, covers the investor-owned utilities' distribution systems,1 so a household served by SMUD in Sacramento deals with SMUD's own rate schedule for customer generation.4

The interconnection process, step by step

The order of steps is similar across utilities, but each has its own forms and names.

1. Application. Consumers Energy in Michigan asks for a Level 1–3 Interconnection Application with contact information, generation type, system size and annual energy use.5 PG&E takes applications through its online portal under Rule 21.6

2. Review level. Utilities sort applications by size, and the review gets deeper as systems grow. Florida's rule uses three tiers; FPL describes Tier 2 as 10 to 100 kW and Tier 3 as 100 kW to 2 MW. Rocky Mountain Power in Utah uses Level 1, Level 2 and Level 3 reviews, each with its own fee.9 The median home system installed in 2025 was 7.7 kW7, below the 10 kW where FPL's Tier 2 begins.8

3. Size checks. The application is where a system that is too large gets caught. Rocky Mountain Power's Schedule 137 covers residential facilities of not more than 25 kW.9 TEP's export rider requires a generating capacity no greater than 125% of the customer's total connected load.10 Consumers Energy limits a generator to 110% of the home's historical 12-month usage.5 PG&E's Solar Billing Plan wants a system intended primarily to offset the customer's own load, but allows a larger one for expected future usage if the customer signs the NBT Oversized Generating Facility Attestation.6

4. Testing and the meter. Georgia Power's interconnection fee covers processing the application, witness testing and reprogramming the meter for projects under 250 kW AC.11 Net billing also changes what the meter records: on PG&E's Solar Billing Plan, the revenue meter keeps imports and exports in separate Import and Export Channels, and the two are not netted.6

5. Agreement and permission to operate. The signed agreement is what the tariff refers back to. FPL's net metering billing applies to customers who "have executed an Interconnection Agreement for Customer-Owned Renewable Generation".12 PTO is the last step, and its date becomes a reference point in the tariff, as the next sections show.

What interconnection costs

Application fees for a home system are set in the tariff or the state rule, and some states rule them out for small systems.

Utility or stateInterconnection fee rule
Florida investor-owned utilitiesTier 1 customers may not be charged fees beyond those of customers without self-generation, "including application fees"13
FPL, Tier 2 and Tier 3Proof of liability insurance and an application fee8
Rocky Mountain Power, UtahLevel 1 $60 per application; Level 2 $75 plus $1.50 per kW; Level 3 $150 plus $3.00 per kW9
Consumers Energy, Michigan$50 with the interconnection application5
PG&E, CaliforniaAn application fee as provided in Electric Rule 21, paid through the online portal6
Alaska (RCA-regulated utilities)No additional interconnection fee unless the Regulatory Commission approves it14
WashingtonNo additional interconnection fee or charge unless the utility's regulator or governing body finds that direct costs exceed offsetting benefits15

The application fee is not always the only cost tied to connection. TEP assesses new residential solar customers an incremental monthly charge for part of the cost of the bidirectional meter they need.10

Which date locks your export credit

This is where interconnection stops being paperwork. Successor tariffs and grandfathering rules are written around interconnection milestones, and the milestone differs from one tariff to the next: the application date, the PTO date, or the date the system was interconnected.

Utility or stateMilestoneWhat it decides
California IOUs (PG&E, SCE, SDG&E)Interconnection application on or after April 15, 2023Service on the Net Billing Tariff instead of NEM 2.016
PG&ECalendar year of the completed interconnection applicationWhich Avoided Cost Calculator values set the nine-year locked export schedule
PG&EPTO dateStart of the nine years the ACC Plus adder stays constant6; for NEM2 customers, start of the 20-year term17
SCEOriginal PTO dateACC Plus only for an original PTO date between April 15, 2023 and December 31, 2027; nine years on the tariff from that date18
TEP, ArizonaWhen the customer requested interconnectionThe RCP export rate kept for up to 10 years1920
APS, ArizonaTime of interconnectionStart of the 10 years the initial RCP rate applies21
Duke Energy, North Carolina (Rider NMB)Interconnection request applicationUp to 15 years on the rider22
ComEd, IllinoisPTO after December 31, 2024Only energy supply credits for exports23
LouisianaInterconnection request or installation after December 31, 2019Exports credited at avoided cost24
Hawaiian ElectricNew interconnection agreementExport rates locked for the first 7 years3
VirginiaFinal interconnectionStart of the 12-month net metering period25

Two practical points follow. First, the application date and the PTO date can fall in different years, and in California they control different parts of the credit: PG&E fixes export values from the Avoided Cost Calculator adopted as of January 1 of the year of the completed application, while the ACC Plus adder runs nine years from PTO.6 Second, a cutoff tied to PTO leaves no room for a slow final inspection. ComEd's change was written around customers "receiving permission to operate" after December 31, 2024.23

Keep the application confirmation, the signed agreement and the PTO letter with the house records. They are the evidence of which tariff applies, and in some places the terms travel with the premises: ComEd says systems eligible for a legacy rate on December 31, 2024 keep it for the lifetime of the system, with later customers inheriting the eligibility.23 Our grandfathering guide covers how long legacy terms last.

Adding panels or a battery later

An interconnection approves a specific system. Changing it can reopen the process and, at some utilities, replace the terms that came with the original approval.

Idaho Power says modifications, which include adding or replacing solar panels or generation equipment, replacing an inverter or adding batteries, "must go through the interconnection process, including a new application".26 APS defines a material increase in capacity as 10% or 1 kW-ac, whichever is greater.21 In Illinois, residential customers interconnected to Ameren or ComEd before January 1, 2025 keep full retail net metering for the life of the system "unless material modifications are made".27

Batteries now arrive with a growing share of new systems: 37% of residential installations in 2025 included one, up from 25%7 in 2024. PG&E's and SCE's tariffs treat a battery installed with the solar system as part of the same interconnection. PG&E gives NBT Paired Storage the same interconnection cost responsibility as the generator it is paired with.6 SCE exempts customers with NBT-Paired Storage Systems under that special condition from Supplemental Review fees, Detailed Study costs and the costs of distribution or network upgrades.18

Batteries paired with net-metered solar, homes, 2025: top 12

Source: Energy Information Administration, Form EIA-861 Annual Electric Power Industry Report, 2025 final data. Residential PV-paired battery installations reported by utilities. Bar colour: program type.

Show the numbers
StateBatteries paired with net-metered solar, homes, 2025
California328K
Hawaii20K
Arizona18K
Utah12K
Texas5,395
Florida5,292
Michigan4,884
New York4,786
Washington3,888
Nevada3,639
New Jersey2,803
Massachusetts2,674
Oregon2,459
Ohio1,943
Colorado1,712
Pennsylvania1,482
Rhode Island1,406
South Carolina1,100
Virginia901
Missouri827
Wisconsin800
New Hampshire777
Maryland753
West Virginia724
Indiana718
Idaho704
Kentucky564
Georgia491
Oklahoma437
North Carolina430
Montana395
Wyoming190
New Mexico133
Minnesota129
Maine114
Arkansas46
Connecticut46
Delaware41
Tennessee39
Illinois30
Iowa23
Nebraska14
Mississippi11
Louisiana4
Kansas2
Alabama0
Alaska0
District of Columbia0
North Dakota0
South Dakota0
Vermont0

Colorado has turned to the connection hardware itself. House Bill 26-1007, approved May 7, 2026, requires the Public Utilities Commission to revise its rules on or before December 31, 2026 so that each qualifying retail utility posts and maintains on its website a public list of at least one approved meter collar adapter.29

When a utility can refuse or limit connection

Approval is not automatic everywhere. Some rules let a utility stop connecting net-metered systems once enough capacity is on its grid.

Alaska's rule lets an electric utility refuse to interconnect a consumer requesting net metering if the total nameplate capacity of participating systems would exceed 1.5 percent of the utility's average retail demand.30 Missouri requires net metering on a first-come, first-served basis until net-metered capacity equals five percent of the retail supplier's single-hour peak load in the previous year.31 Hawaiian Electric's export program has no capacity limit, with system size governed by Rule 14H.3

The number of connections keeps growing. EIA counted 486,43932 more net-metering customers at the end of 2025 than a year earlier, for a national total of 5,904,99228; net-billing customers can be reported outside that count.

Texas: who connects the system and who buys the exports

In the parts of Texas with retail choice, the wires utility (Oncor, CenterPoint, AEP Texas or TNMP) connects and meters the system, but it does not buy the exports. The Public Utility Commission of Texas says that where you can shop for a retail electric plan, the buyback rate "is part of your contract with your electric provider".33 Approval to connect does not, by itself, give a Texas household any export credit; that comes from the retail plan, or from the municipal utility or co-op where there is no retail choice.

Interconnection dates and the federal tax credit

For the homeowner credit, the date on the PTO letter is not the test. Section 25D stops with expenditures made after December 31, 2025, and it dates an expenditure by when the original installation is completed; the utility's permission to operate is not mentioned. Credit that exceeded the year's tax for an installation completed in time carries forward.34

A leased or PPA system follows a different calendar, because the federal credit is the owner's §48E credit: it is not available for solar placed in service after December 31, 202735 when construction began after July 4, 2026,36 and the homeowner claims nothing. The federal solar tax credit page has both sets of dates.

Questions and answers

What is a solar interconnection agreement?

The contract between a solar customer and the utility that sets the terms for connecting and running the system on the utility's grid. Florida Power & Light, for example, applies its net metering billing only to customers who have executed its Interconnection Agreement for Customer-Owned Renewable Generation.12

What does permission to operate mean for solar?

It is the utility's written approval to turn the system on and start exporting. Tariffs use the date as a milestone: PG&E counts the 20-year NEM2 term from the date a customer originally received Permission To Operate.17

How does PG&E solar interconnection work?

PG&E connects home solar under Electric Rule 21. A Solar Billing Plan customer pays for interconnection as provided in Rule 21, including an application fee paid through PG&E's online application portal.6

Can I turn on my solar panels before permission to operate?

Running a system is the step permission to operate approves, and tariffs attach credit terms to that date. In ComEd's territory, customers receiving permission to operate after December 31, 2024 get only energy supply credits for excess energy.23

Do I need a new interconnection application if I add a battery?

At some utilities, yes. Idaho Power says modifications, including adding or replacing panels, replacing an inverter or adding batteries, must go through the interconnection process with a new application.26

Related guides

Sources

  1. CPUC, Electric Rule 21: Generating Facility Interconnections. Electric Rule 21 (Rule 21) is a tariff that describes the interconnection, operating and metering requirements for generation facilities to be connected to an investor-owned utility’s (IOUs) distribution sy[stem] Checked November 16, 2026. cpuc.ca.gov
  2. Rule 25-6.065, F.A.C. (Florida PSC), text from flrules.org rule document. (e) During any billing cycle, excess customer-owned renewable generation delivered to the investor-owned utility’s electric grid shall be credited to the customer’s [next] billing cycle. (f) Energy credits produced pursuant to paragraph (8)(e) shall accumulate and be used to offset the customer’s … Checked November 16, 2026. flrules.org
  3. Hawaiian Electric – Smart Renewable Energy Export program page, Hawaiian Electric web page, checked 2026-11-16. Smart Renewable Energy (SRE) - Export rates for 2024-2026 Island Overnight (9pm - 9am) Daytime (9am - 5pm) Evening Peak (5pm - 9pm) Oahu 18.9 cents/kWh* 13.5 cents/kWh* 32.9 cents/kWh* Maui 13.1 cents/kWh* 6.6 cents/kWh* 18.2 cents/kWh* … Export credits will be trued-up on an annual basis and any … Checked November 16, 2026. hawaiianelectric.com
  4. SMUD Rate Schedule SSR – Solar and Storage Rate, Sheets SSR-1 to SSR-3; Resolution No. 21-09-07 (Sept 16, 2021) as amended by Resolution No. 26-04-04 (April 16, 2026); effective June 1, 2026. This Rate Schedule SSR applies to residential, commercial/industrial, and agricultural customers who establish service at a premises that has an electrical generation facility that is fueled by a renewable fuel source on or after March 1, 2022 … The Export Compensation Rate effective June 1, 2026 … Checked November 16, 2026. smud.org
  5. Consumers Energy – Distributed Generation (residential) page, Consumers Energy web page, checked 2026-11-16. Your generator offsets the electric needs of your home or business, up to 110% of your historical 12-month usage. … Credit Excess energy credited at power supply rate including transmission. See Tariff chart C.11.3 for more detail. Note: As of 2/27/2024, Distributed Generation credits will be … Checked November 16, 2026. consumersenergy.com
  6. PG&E Electric Schedule NBT – Net Billing Tariff (NBT) Service, Cal. P.U.C. Sheets 55440-E et seq.; Advice 6848-E (eff. 2023-03-01), Advice 7174-E (eff. 2024-02-15); CPUC D.22-12-056, D.23-11-068. The NBT schedule may also be referred to as the Solar Billing Plan in customer-facing communications. Residential customers, including Load Aggregation Generating/Aggregated Accounts, taking service on NBT must take service on the E-ELEC (ELECTRIC HOME) rate schedule … For both residential and … Checked November 16, 2026. pge.com
  7. Lawrence Berkeley National Laboratory, U.S. Distributed Solar and Storage, 2026 Data Update, Median installed prices of host-owned residential PV installed in 2025, released August 1, 2026. emp.lbl.gov
  8. FPL Net Metering FAQ, FPL web page. Tier 2, (10 to 100 kW) and Tier 3 (100 kW to 2 MW) systems also require proof of liability insurance and an application fee. Checked November 16, 2026. fpl.com
  9. Rocky Mountain Power Utah Electric Service Schedule No. 137 – Net Billing Service, P.S.C.U. No. 52; Sheet 137.1 & 137.4 (Docket 24-035-04, eff. Apr 25, 2025); First Revision Sheet 137.3 (Docket 26-035-T03, filed Jan 26, 2026, eff. Mar 1, 2026). with a capacity of not more than twenty-five (25) kilowatts for a residential facility or two (2) megawatts for a non-residential facility … Billing Months – June through September inclusive 4.855¢ per kWh for all exported kWh Billing Months – October through May inclusive 4.033¢ per kWh for all … Checked November 16, 2026. rockymountainpower.net
  10. TEP Rider R-14, Resource Comparison Proxy Export Rate (RCP-PRS), Sheet No. 714, Original Sheet 714-0/714-1, effective September 1, 2023, ACC Decision No. 79065. The Company will meter this export power on an instantaneous basis and provide a monthly bill credit based on the purchase rate in this schedule. ... 3. Each Customer’s initial RCP rate will be applicable for 10 years from the time of their interconnection. … Each calendar year, for the customer … Checked November 16, 2026. docs.tep.com
  11. Georgia Power – Residential Rooftop Solar FAQs, Georgia Power web page, checked 2026-11-16. excess energy generated by a customer's solar panels are credited at the annual Solar Avoided Cost Rate per kilowatt hour (kWh), which is 3.2188 ¢/kWh for the year 2026. During the 2022 rate case, the Public Service Commission approved an additional 4¢/kWh that will be added to the annual solar … Checked November 16, 2026. georgiapower.com
  12. FPL Electric Tariff Section 10 – Eighteenth Revised Sheet No. 10.010 "Contract Provisions – Various" (Net Metering of Customer-Owned Renewable Generation), Sheet No. 10.010, effective January 1, 2026. For Customers with renewable generation equipment up to a maximum of 2 MW that have executed an Interconnection Agreement for Customer-Owned Renewable Generation with the Company, the following billing parameters will apply. … If any excess customer-owned renewable generation is delivered to the … Checked November 16, 2026. fpl.com
  13. Florida PSC Rule 25-6.065, F.A.C., Interconnection and Net Metering of Customer-Owned Renewable Generation (as adopted by Order No. PSC-08-0161-FOF-EI, Docket 070674-EI; copy hosted by FPL), Rule 25-6.065 F.A.C.. Tier 1 customers who request interconnection of customer-owned renewable generation shall not be charged fees in addition to those charged to other retail customers without self-generation, including application fees. Checked November 16, 2026. fpl.com
  14. 3 AAC 50.930 Charges or credits for net electric energy. the electric utility shall credit the consumer's account with an amount derived by multiplying the kilowatt-hours of net electric energy supplied by the consumer to the electric utility by the non-firm power rate contained in the electric utility's currently effective tariff ... (2) do not expire … Checked November 16, 2026. akleg.gov
  15. RCW 80.60.020. (a) Shall offer to make net metering, pursuant to RCW 80.60.030 , available to eligible customer-generators on a first-come, first-served basis until the earlier of either: (i) June 30, 2029; or (ii) the first date upon which the cumulative generating capacity of net metering systems equals four … Checked November 16, 2026. app.leg.wa.gov
  16. CPUC – Net Billing Tariff page, CPUC web page. On December 15, 2022, the CPUC adopted D.22-12-056, establishing the Net Billing tariff (NBT) as a successor to NEM2. ... The NBT will apply to customers who submit an interconnection application on or after April 15, 2023. Checked November 16, 2026. cpuc.ca.gov
  17. PG&E Electric Schedule NEM2 – Net Energy Metering Service, Cal. P.U.C. Sheet 59228-E (Sheet 46) et seq.; CPUC D.16-01-044. are eligible to continue receiving service on this NEM2 Schedule for a period of 20 years from the original year in which their Generating Facility was interconnected to PG&E’s grid, indicated by and measured from the date on which the Customer originally received Permission To Operate (PTO) … … Checked November 16, 2026. pge.com
  18. SCE Schedule NBT – Net Billing Tariff, Cal. PUC Sheets 85375-E et seq. (e.g., Sheet 30 = 87700-E); Advice 4961-E/4961-E-A (eff. 2023-03-01), 5170-E-A (eff. 2023-12-14), 5228-E (eff. 2024-02-15), 5533-E (eff. 2025-04-23); D.22-12-056; D.23-11-068. Residential Customers taking service under this Schedule must be on the Prime Option of Schedule TOU-D. … multiplying the hourly-differentiated Customer’s Energy Export (channel 2) in kWh by the applicable Energy Export Credit Price (EEC Price), as defined below, derived from the approved Avoided … Checked November 16, 2026. sce.com
  19. Tucson Electric Power, Resource Comparison Proxy Export Rate. Effective: 2026-10-01. customers are compensated for up to 10 years at the RCP export rate in place at the time they requested interconnection of a new solar power system. ... An energy export rate of $0.0462 per kWh will remain in effect from October 1, 2026 through September 30, 2027. ... Rules approved by the ACC call … Checked November 16, 2026. tep.com
  20. APS, Renewable Energy Riders (RCP Export Rider, EPR-6, Legacy EPR-6). aps Resource Comparison Proxy (RCP) is a net billing solar purchase energy rider, it measures the excess power you don't use and gives you a monthly bill credit based on the current RCP purchase rate. The credit will apply towards your APS billed amount for that month, and any remaining credit will … Checked November 16, 2026. aps.com
  21. APS Rate Rider RCP – Partial Requirements Service for New On-Site Solar DG, Resource Comparison Proxy Export Rate, A.C.C. No. 6248, Revision No. 11, effective September 1, 2026 in ACC Decision No. 82122. The Company will meter this Export Energy on an instantaneous basis and provide a monthly bill credit based on the purchase rate in this schedule. … Tranche 2025 September 1, 2025 through August 31, 2026 $0.06171 per kWh Tranche 2026 September 1, 2026 through August 31, 2027 $0.05554 per kWh … An … Checked November 16, 2026. aps.com
  22. NC Public Staff – Net Metering (summary of NCUC Order Approving Revised Net Metering Tariffs, Docket E-100, Sub 180, March 23, 2023, and Order Granting Extension of Time, May 17, 2023), NCUC Docket No. E-100, Sub 180. The current residential net metering rider (Rider NM) is closed to new customers as of September 30, 2023. The revised Net Metering riders (Residential Solar Choice (Rider RSC) and Net Metering Bridge (Rider NMB)) are effective October 1, 2023 for residential customers. … the excess energy you … Checked November 16, 2026. publicstaff.nc.gov
  23. ComEd, "2025 Changes to Net Metering" (062024), ComEd customer document, 2024; implements CEJA (P.A. 102-0662). Full retail rate net metering will no longer be available to customers interconnecting renewable energy systems after December 31, 2024. Customers receiving permission to operate after such date will be eligible to receive only energy supply credits for their excess energy sent back to the grid. … … Checked November 16, 2026. azure-na-assets.contentstack.com
  24. Louisiana PSC, "Avoided Cost Rate by Electric Utility 2024", LPSC General Order dated September 19, 2019 (Distributed Generation Rules); list updated March 31, 2024. customers who submit an interconnection request and/or install a distributed generation facility after December 31, 2019 shall pay the full retail rate for all energy purchased from the utility, shall pay a zero rate for all energy self-generated and consumed, and shall be credited at Avoided Cost … Checked November 16, 2026. lpsc.louisiana.gov
  25. Va. Code §56-594 Net energy metering provisions (both versions: until and from Jan 1, 2027). (i) has a capacity of not more than 25 kilowatts for residential customers and not more than three megawatts for nonresidential customers ... "Net metering period" means the 12-month period following the date of final interconnection ... until the rated generating capacity ... reaches six percent, … Checked November 16, 2026. law.lis.virginia.gov
  26. Idaho Power, "Important Reminder For Your Renewable Energy System 2026" (customer generation brochure, 31180-I-0391), Idaho Power brochure (2026). Export Credit Rate Summer On-Peak ..... 15.6836 per kilowatt-hour (kWh) Off-Peak ..... 3.3920 per kWh Non-Summer On-Peak ..... N/A Off-Peak ..... 2.9019 per kWh ... These rates are effective as of Oct. 1, 2025. … A Net Billing customer shall receive a credit for Exported Energy at the applicable … Checked November 16, 2026. docs.idahopower.com
  27. Illinois Shines (Illinois Power Agency), FAQs Related to Changes in Net Metering in Illinois - Consumers (26 July 2024). Effective: 2025-01-01. Under Illinois law, customers beginning net metering service on or after January 1, 2025 will receive net metering just for supply charges, rather than the full retail rate net metering. ... Residential and small commercial customers interconnected to Ameren or ComEd prior to January 1, 2025 who … Checked November 16, 2026. illinoisshines.com
  28. Energy Information Administration, Form EIA-861 Annual Electric Power Industry Report, 2025 final data, Net_Metering_2025.xlsx (f8612025.zip), released October 7, 2026. eia.gov
  29. Colorado Session Laws 2026, Ch. 127, House Bill 26-1007. Effective: ~2026-08-12 (90 days after adjournment). (1.3) ON OR BEFORE DECEMBER 31, 2026, THE COMMISSION SHALL REVISE EXISTING RULES TO: (a) REQUIRE A QUALIFYING RETAIL UTILITY TO POST AND MAINTAIN ON ITS WEBSITE A PUBLIC LIST OF AT LEAST ONE METER COLLAR ADAPTER ... (VII) ON AND AFTER JANUARY 1, 2027, A PORTABLE-SCALE SOLAR GENERATION DEVICE, AS … Checked November 16, 2026. leg.colorado.gov
  30. 3 AAC 50.910 Net metering of electric energy. An electric utility may refuse to interconnect with a consumer requesting net metering, if interconnection would cause the total nameplate capacity of all eligible consumer generation systems participating in the net metering program to exceed 1.5 percent of the electric utility's average retail demand Checked November 16, 2026. akleg.gov
  31. RSMo 386.890 Net metering and easy connection act. (b) Has an electrical generating system with a capacity of not more than one hundred kilowatts ... (1) Make net metering available to customer-generators on a first-come, first-served basis until the total rated generating capacity of net metering systems equals five percent of the retail electric … Checked November 16, 2026. revisor.mo.gov
  32. Energy Information Administration, Form EIA-861 Annual Electric Power Industry Report, net metering 2010–2025, Net_Metering sheets of the annual files, released October 7, 2026. eia.gov
  33. PUCT 'Solar Guide for Consumers' (March 2026) - PUCT publication, copy hosted by City of Bellville. Effective: March 2026. Buyback rate is the price you are paid for any electricity you put back onto the grid. • Rules for the buyback rate depend on what kind of provider you have. • In areas where you can shop for your retail electric plan, you can shop for a plan with a buyback rate and other features. ... The buyback … Checked November 16, 2026. cityofbellville.com
  34. 26 U.S.C. §25D, Residential clean energy credit, Text current through Public Law 119-142 (November 10, 2026). in the case of property placed in service after December 31, 2021, 30 percent … The credit allowed under this section shall not apply with respect to any expenditures made after December 31, 2025. … an expenditure with respect to an item shall be treated as made when the original installation of … Checked November 16, 2026. uscode.house.gov
  35. 26 U.S.C. §48E, Clean electricity investment credit, Text current through Public Law 119-142 (November 10, 2026). with a maximum net output of less than 1 megawatt (as measured in alternating current) … This section shall not apply to any qualified property placed in service by the taxpayer after December 31, 2027, which is part of an applicable facility. … This paragraph shall not apply with respect to any … Checked November 16, 2026. uscode.house.gov
  36. Public Law 119-21 (July 4, 2025), sections 70506 and 70513, 139 Stat. 72. Section 25D(h) is amended by striking ``to property placed in service after December 31, 2034'' and inserting ``with respect to any expenditures made after December 31, 2025'' … shall apply to facilities the construction of which begins after the date which is 12 months after the date of enactment of this Act Checked November 16, 2026. govinfo.gov

Rules are quoted from the official text and dated; how we check them: methodology. Not legal or tax advice. Found an error? Write to [email protected]; corrections are listed on the updates page.